According to the project and details,

· Aypan TU profiles made of galvanized steel sheet according to TS EN 14195 should be fixed to the base and ceiling by using Aypan screws and plastic dowels at 60 cm intervals.

· TC 60 profiles should be cut.

· Before fixing, 50 mm Aypan sound insulation tape should be adhered to the back of TU profiles and frames.

· Aypan agraffee should be fixed to the existing wall with Aypan screws and plastic dowels at maximum 60 cm intervals in vertical and 60 cm intervals in horizontal.

· The Aypan chafing wings should be adjusted by bending according to the wall position.

· TC 60 profiles should be placed between two wings of Aypan plates and inserted between TU 28 profiles. Aypan brackets should be fixed to both blades of TC 60 profiles with Aypan brackets.

· 12.5 mm Aypan should be fixed to TU 28 and TC 60 profiles with 25 mm Aypan self-tapping screws. If necessary, Aypan should be cut and sized.

· Pre-fill the gaps more than 3 mm with Aygips grouting plaster. Joint tape should be adhered to Aypan joints.

· The cladding wall should be formed by applying Aygips joint filler plaster on the joint tape.

The price is 1 m2 including all kinds of materials and losses, loading in the workplace, horizontal and vertical transport, unloading and contractor profit and general expenses.

Quantities

Prodoct Code Material Name 40 cm** 60 cm** Unit
AL125BY250 AYPAN (12,5 mm) 1,00 1,00
AK60ETC300 AYPAN TC 60 Profile  2,80 2,00 m
AK30ETU300 AYPAN TU 28 Profile 0,80 0,80 m
BN050YB025 AYPAN Noice Reduction Tape 1,30 1,30 m
AB030AG120 AYPAN Agraffee 2,20 1,50 pcs
AB042MB000 AYPAN Button Headed Screw 1,30 1,30 pcs
AB048DV145 AYPAN Plastic Dowel and Pan Head Screw Set 2,20 2,20 pcs
AB035BV025 AYPAN Drywall Screw 3,5x25 mm  19,00 15,00 pcs
BN050DB090 AYPAN Joınt Tape 1,40 1,40 m
AG001DD025 AYGIPS Joing Filling Plaster 0,40 0,40 kg
  Rock wool 1,00 1,00
   
AG001ST025 AYGIPS Satin Finishing Plaster For each one mm kg
AK022DP270 AYPAN Perforated Corner Profile As per project m
              
A DOOR SYSTEM ANALYZE
Malzeme Adı Quantities Unit
Door Supported Stud    
L Bracket Somun Bolt Set    
Steel anchor    
*Without wastage  
**TC Stud axis gap
***Based on 4X2,5 mt wall measurements.

 

Performance

It is a cladding wall system applied with metal skeleton on the wall such as brick, pumice, gas concrete. Agraf is made using TU and TC profiles. One layer of Aypan is screwed onto the Aypan TC profiles.

  • It can be used in order to obtain a smooth surface on the scales and broken walls.
  • It can be used in cases where it is desired to increase the thermal and sound insulation performance of the existing wall.
  • The system is light, does not put too much load on the building. Minimizes loss of life and property against seismic loads.
  • It is also used to hide and close the installation if the installation passes in front of the wall or surface. It is also used in repair and renovation works.
  • The average weight of the system is 15 kg / m2.
  • The sound insulation performance of the system with the existing wall is between 53-71 dB.
  • The distance between the existing wall and the Aypan coating surface can be covered up to 120 mm.
  • Walls should be fixed to TC profiles with maximum 125 cm intervals.
  • The gap between the profiles can be used as installation passage.
  • Optionally, rockwool insulation plates can be placed between the profiles.
  • Easy to apply, fast and economical.